City Governance Project (CGP)
List of Batch-1 Projects
Sl. No. |
Name of Sub-Project with ID |
Quantity km/m/ Nos. |
Estimated Cost (TK). |
Contract Amount (TK) |
Original |
||||
1 |
2 |
3 |
4 |
5 |
1 |
Rehabilitation and upgradiation of Zakir Hossain road by RCC/BC from G.E.C to Women college junction at Ch 00m – 1000.00m (Rehabilitation and upgradiation of Zakir Hossain road by RCC/BC fron G.E.C to Women college junction at Ch 00m – 800.00m and Link Women college-lord in more ch 00-500m). ICGP B1 ChCC 01 Tender ID: 31280 |
1.3 K.M. |
5,06,30,037.00 |
4,19,83136.23 |
2 |
Rehabilitation and upgradiation of Zakir Hossain road by RCC/BC from Women college junction to Dhaka trunk road at ch 1000m – 4500.00m (Rehabilitation and upgradiation of Zakir Hossain road by RCC/BC from Women college junction to Dhaka trunk road at ch 800m – 4505.00m and link-1 Fays lake road ch00-450m link-2 Feroz Shah 2 no lane road ch 00-370m). ICGP B1 ChCC 02 Tender ID: 31290 |
4.53 K.M. |
17,20,62,313.00 |
14,31,24,162.094 |
3 |
Extension of Airport Road from solgola to cement crossing by RCC/BC along with footpath and roadside drain (Chanage 00-7000.00m) ICGP B1 ChCC 03 Tender ID: 27000 |
7.00 K.M. |
21,71,37,332.00 |
18,35,75,992.652 |
4 |
Extension of Airport Road from solgola to cement crossing by RCC/BC along with footpath and road side drain ( Chanage 7000m-11550m) ICGP B1 ChCC 04 Tender ID: 27001 |
4.55 KM |
11,75,04,781.00 |
10,16,88,179.9 |
6 |
Improvement of Mariner's Road Starting from Firingee bazar to Chakti bridge and Chaktai Shah Amanat New bridge road by RCC (Chainge 00-1160m) ICGP B1 ChCC 06 Tender ID: 27002 |
1.16 KM |
8,19,22,410.00 |
6,99,95,195.36 |
7 |
Construction of 14m span RCC bridge(Initially proposed20m in DPP) beside Rubi cement at airport road. ICGP B1 ChCC 07 Tender ID: 25986 |
14.00 M |
1,94,93,178.00 |
1,75,04,858.161 |
8 |
Construction of 20 m span RCC Girder bridge at 9 No GoptaKhal. ICGP B1 ChCC 08 Tender ID: 25998 |
20.00 M |
2,13,81,683.00 |
1,84,97,076.313 |
9 |
Construction of 60 m span RCC Girder bridge at 15 No Khal at ward 40/41. (Construction of 40m span PC girder bridge 15 no khal at air port road ward no 40/41) ICGP B1 ChCC 09 Tender ID:27003 |
40.00 M |
6,56,76,468.00 |
5,61,79,460.945 |
10 |
Construction of 60 m span Chaktai P. C. Girder Bridge (Construction of 60m span PC and RCC Girder bridge over Chaktaikhal on Mariner’s road at Ch. 960.00m) ICGP B1 ChCC 10 Tender ID: 27004 |
60.00 M |
4,81,13,465.00 |
4,08,63,270.937 |
11 |
Construction of 19.26 m span (Initially 20m in DPP)Fishereeghat Bridge at Fishereeghat. ICGP B1 ChCC 11 Tender ID: 26058 |
19.26 M |
1,86,81,091.00 |
1,80,89,499.638 |
12 |
Construction of 20.34 m span Jalilgonj(Initially 20m P. C. Girder in DPP) RCC Girder Bridge at Jalilgonj. ICGP B1 ChCC 12 Tender ID: 26059 |
20.34 M |
1,90,20,224.00 |
1,63,43,013.625 |
13 |
Construction of 17.70( Initially 20m P.C Girder in DPP) Tackpara RCC Girder Bridge at Tackpara. ICGP B1 ChCC 13 Tender ID: 26065 |
17.70 M |
1,90,40,245.00 |
1,59,44,085.563 |
14 |
Construction of Retaining wall on both side of MoheshKhal in Ward 26 & improvement of Road by RCC .ICGP B1 ChCC 14 Tender ID: |
4.00K.M |
41,02,75,232.00 |
|
15 |
Construction of Retaning wall with improvement of road by RCC from NimtolaBimanChottor to Abdul latif Road in ward 27 & 36 at Ch 00-1220 m &Ch 00-193 m. |
1.41 K.M. |
13,31,10,954.00 |
11,78,99,571.688 |
16 |
Construction of Retaining wall at MoheshKhal in Ward 36 & improvement of Road by RCC at Ch 00-2799.00 m. |
2.8 K.M. |
26,83,19,846.00 |
26,20,00,342.885 |
17 |
Construction of retaining wall at diversion khal side including road improvement by RCC/BC at Bakalia ward -17 at Ch00-600.00 m. |
0.6 K.M. |
5,67,98,452.00 |
4,92,27,694.00 |
18 |
Construction of retaining wall at Birjakhal of sayed shah road and beside the Shorubi R/A. Khal including side road by RCC/BC at Ch oo-830.00 |
0.83 K.M. |
7,72,89,814.00 |
6,98,35,235.924 |
Total= |
179,64,57,525.00 |
110,48,51,204.227 |
List of Batch-2 Projects
Package No. |
Sub-Sector |
Name of Sub-projects/Scheme |
Quantity |
Unit |
Package Amount (Crore) |
1 |
2 |
3 |
4 |
5 |
6 |
Chittagong CC: Batch-2 |
|||||
ChCC-1 |
Road improvement |
Improvement of port connecting Road by RCC from Andorkilla to Nimtola. (Ch-0.00km-2.00km) |
2.00 |
km |
39.67 |
ChCC-2 |
Road improvement |
Improvement of port connecting Road by RCC from Andorkilla to Nimtola. (Ch-2.00km-4.00km) |
2.00 |
km |
39.67 |
ChCC-3 |
Road improvement |
Improvement of port connecting Road by RCC from Andorkilla to Nimtola. (Ch-4.00km-6.00km) |
2.00 |
km |
39.67 |
ChCC-4 |
Road improvement |
Improvement of Agrabad access Road by over lay and wideining with RCC |
2.00 |
km |
45.83 |
ChCC-5 |
Bridge/overpass |
Construction of 1200 m long overpass starting from Sagarika road Alankar crossing to A.K.khan Crossing |
1200.00 |
m |
106.43 |
ChCC-6 |
Bridge/overpass |
Construction of 650 m long overpass at Jakir Hossain Road Rail Crossing (1) |
650.00 |
m |
36.08 |
ChCC-7 |
Bridge/overpass |
Construction of 650 m long overpass at New Market Crossing |
650.00 |
m |
36.23 |
ChCC-8 |
School/cum cyclone center |
New construction of six stored building at Patanga girl's high school & college cum cyclone shulter |
1.00 |
nos |
12.45 |
ChCC-9 |
School/cum cyclone center |
New construction of Mohabbat Ali girl's High school cum cyclone shulter |
1.00 |
nos |
6.49 |
ChCC-10 |
School/cum cyclone center |
New construction of Ahmed Mia City Corp. girl's school cum cyclone shulter |
1.00 |
nos |
9.97 |
ChCC-11 |
School/cum cyclone center |
Re-construction of Lldighi central disaster management control office, library and community center cum cyclone |
1.00 |
nos |
21.95 |
ChCC-12 |
School/cum cyclone center |
Re-condtruction of East Madarbari girls high school cum cyclone center |
1.00 |
nos |
7.98 |
ChCC-13 |
School/cum cyclone center |
Re-condtruction of West Madarbari girls high school cum cyclone center |
1.00 |
nos |
7.76 |
ChCC-14 |
School/cum cyclone center |
New construction of Patantually boys high school cum cyclone center |
1.00 |
nos |
7.76 |
ChCC-15 |
School/cum cyclone center |
New construction of RabindraNazrul high school cum cyclone center |
1.00 |
nos |
11.64 |
ChCC-16 |
School/cum cyclone center |
Construction of 65m Bridge on Marinars Road |
65.00 |
m |
5.5 |
ChCC-17 |
Road improvement |
Re-construction of road by RCC from SotsongAsromNibashi to Soroni Road (2.0km) |
2.00 |
km |
9 |
Total |
444.08 |
September 2016 progress Report B-1
October 2016 progress Report (Update)
November 2016 progress Report(Update)
December 2016 Monthly Progress Report
January 2017 Monthly Progress Report
August 2017 progress Report B1